Hi all
Can I use planning area SAPIBP1 for order based planning as SAP74?
If not, do I need one planning area for S&OP and other for order based planning?And how can I transfer data from one planning area to another?
Can I used one planning area for everything?
Thanks
Hi Carlos
Response & Supply will be available in IBP 1802 release. Till then you have to manage it via separate planning area. For transferring KF values between the planning area you have to extract from IBP1 and upload in SAP74 PA using HCI and SDI.
Regards
Ankur