Hi there,

I’m contacting you about an issue we are occuring.

How can we transfer in ByDesign a massive number of fixed asset from a cost center to another one ?

Could you please help us to find a technical way to facilitate this operation as it needs days and days to do it manually

Thanks

Damien

0 Kudos

Just wondering if there has been any movement on this. Is there a way, yet, to do a mass transfer of fixed assets from one cost center to another?

Thanks!

Julie

Accepted Solutions (0)

Answers (1)

Answers (1)

manasa_a
Employee
Employee
0 Kudos

Dear Damien,

Did you mean transferring of fixed asset balances from one cost center to another cost center ??

Kindly explain the scenario in detail.

Thanks & Regards,

Manasa

0 Kudos

Hi I am also looking into a way of mass transfering a fixed asset from one cost center to another cost center.

The manual way will take a long time since our customer has over 1300 fixed assets. Is there a way to currently do this?

manasa_a
Employee
Employee
0 Kudos

Hi Adriel,

Unfortunatey,currently there is no way to transfer fixed assets in mass from one cost center to another cost center.

Thanks & Regards,