on 09-24-2017 10:38 AM
Our SAP system is set up to automatically update the start date in the WO when the project schedule is updated. This may push the component requirement date in or out.
However this does not automatically update the component requirement date on the PO's for those components that are sent to a third part vendor.
Is there a tcode where I can run a report that compares the requirement date on the WO to the requirement date on the corresponding PO's?
We could then manually update the dates on the PO's and send the revised PO's to the vendor.
Thanks!
Dear TJ,
What does WO and PO standard for? May I know the full name? Also appreciate if you can send some screenshots to explain this question.
best regards,
Jessica
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.