Raw Materials planning considering Lead time and next month requirement

Sep 25, 2017 at 11:48 AM

34

avatar image

Hi,

I have scenario in which RM quantity should be calculated on the basis of current month requirement and partly next month requirement if lead time is more than 30 days.

E.g.

RM Req for current month = 100 QTY

RM req for next month = 200 QTY = 7 Qty / day

Total Lead time = 35 days

Then Required Qty = 100 + (7*5) = 130.

Regards,

Amarnath Dube

10 |10000 characters needed characters left characters exceeded

Hi ,

Still waiting for the answers.