Dear experts,

Unable to inactivate the material i.e by setting deletion flags at different organizational levels, for example, at plant level or/ setting a deletion flag at client level.

After setting deletion flags and on submit the MDGM CR, the CR going into Status: 11( Process Errors After Activation) error.

Can anyone help me in identifying the root cause or how to eliminate the error?

Note : WF-BATCH user does not have any authorization errors.

Thanks

Accepted Solutions (0)

Answers (4)

Answers (4)

partha_kar2
Active Participant
0 Kudos

Did you happen to check the 'Validation Log" of that error-ed CR?

Additionally, please check the below:

1. Activate the CR if it is with someone now after activation failure

2. Check for authorizations with the person/role/WF-admin performing the final activation

0 Kudos

Hi All ,

Do you have any way to find out the reason for the error? Even we are facing the same error while activating the CR for creation of material.

Regards,

Anshuman

bpawanchand
Active Contributor
0 Kudos

Hi Ashwini

Have you tried to check from SLG1 by using the object as "FMDM" subobject as "CREQUEST" ?

Regards

Pavan

loga201
Contributor
0 Kudos

Hi,

Check Validation log either from CR or SLG1 also check for dumps in st22. If you dont really get any clue then one option would be to debug excution logic.

Thanks and Regards,

Logan.D

varun_jain3
Active Participant
0 Kudos

HI Santhosh,

GO to SLG1 and chek error.

Varun

0 Kudos

Hi Varun,

SLG1 Logs only shows generic message i.e Internal error. Notify your system administrator.By this message we cannot identify the cause of the issue.