cancel
Showing results for 
Search instead for 
Did you mean: 

Period in /sapapo/delete_pp_order

former_member245593
Discoverer
0 Kudos

Hello!

Colleagues, may be you have some information about period dates in /sapapo/delete_pp_order:

Start date

Finish Date

What is meant under start\finish date? Are they start and finish of an order or an operation? Or something else?

Unfortunately we couldn’t find any detailed information about them.

The matter is that when we are trying to delete planned orders with category AI in particular period (this period we set using these start\finish dates) program /sapapo/delete_pp_order deletes all “AI” planned orders on the whole PP\DS horizon.

Thank you!

Accepted Solutions (1)

Accepted Solutions (1)

Hi Anastasia,

The report selects I/O nodes for deletion. As such the Availability Date/Requirements Date (or the Continuous Scheduling Date) of the Receipt/Demand you'd like to delete must be within the selection horizon.

Example:

The Availability Date is 18.08.2016 12:00:00, so if you enter a horizon that ends before this date/time or that starts after it, the receipt should not be selected even if there is some processing activity going on at the moment.

If you do not specify a horizon, all nodes will be selected, regardless of their dates.

Regards,
Tiago

Answers (0)