Skip to Content
0
Former Member
Oct 24, 2007 at 04:54 PM

Project system: error when confirm an activity

42 Views

Hi Gurus,

I try to confirm an activity ( TC: CJ20N ). I go through "Edit / Activity / Confirm" but I get following message NO VALID CAPACITY FOR FINITE SCHEDULING (mssg Nr. C7 057).

However I already confirmed an activity assigned to the same work center.

Do you have any explanation what why the error message occurs???

What does the indicator relevant for finite scheduling mean?

Please advice!

Thanks