Required splitting operation in routing have costing problem

suresh_bachan
Active Participant
0 Kudos

Dear all,

We have defined a "Required splitting" in a routing for a scheduling purpose which is working fine. This means the operation can be processed in parallel with the number of individuals / machines indicated in the "maximum number of splits".

Example: if the total labor time needed for the operation is 20 hours & the maximum number of splits is 4, system will distribute to 4 individual capacities and schedules 5h.

The scheduling part works fine but when we create costing(CK11N) for the finished material using this routing, only 5h are calculated instead of the total time needed, which is 20h.

Is there a missing setting for this?

Thanks in advance for your help

suresh_bachan
Active Participant
0 Kudos

Can someone please help me with this problem?

Accepted Solutions (1)

Accepted Solutions (1)

dheeraj_maloo
Explorer
0 Kudos

Hi Suresh,

Pl try changing the formula used for calculating the activity assigned in costing tab of work center. You need to insert the formula with operation split as a part of it.

Thanks,

Dheeraj