on 09-22-2017 8:25 AM
Dear all,
We have defined a "Required splitting" in a routing for a scheduling purpose which is working fine. This means the operation can be processed in parallel with the number of individuals / machines indicated in the "maximum number of splits".
Example: if the total labor time needed for the operation is 20 hours & the maximum number of splits is 4, system will distribute to 4 individual capacities and schedules 5h.
The scheduling part works fine but when we create costing(CK11N) for the finished material using this routing, only 5h are calculated instead of the total time needed, which is 20h.
Is there a missing setting for this?
Thanks in advance for your help
Hi Suresh,
Pl try changing the formula used for calculating the activity assigned in costing tab of work center. You need to insert the formula with operation split as a part of it.
Thanks,
Dheeraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.