There is a material in which we have different batches, SLED is maintained in the master data of that material. Quality have changed the SLED of a specific batch through MSC2N. But when a cycle count or migo is posted system changes automatically changes the SLED and revert back it to the one maintained in master data.

Can we prevent transactions like cycle count or migo to not change the SLED?

We still require SLED to be picked up from master data at the time of production or procurement, but if the value of a batch is changed at anytime afterwards, the system should not try and reset it according to the master data.