Incorrect cost plan in a network activity

Hi All,

Automatic cost calculation in Network activity is incorrect. The Service Activity only has a service material with a value of 34,680.00 and the value of the calculation is 104,040.00 (KPPP in COSP / RPSCO). I executed the CJEN transaction, but the inconsistency continues.

Thanks in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Sep 24, 2017 at 05:09 AM

    Hi

    Can you check in report S_ALR_87013532 - Plan/Actual/Variance and provide us a screenshot ?

    Also check the currency field, is the Transaction Currency / Object Curreny / Controlling Area Currency, is all same.

    Regards

    Terence