on 10-23-2007 11:56 AM
Hello Freinds,
I am working on SRM 4.0 classic scenario. The requiremnts are not getting cleared although follow on docs are created for them ( PO). This is happening for only service shopping carts and not for the goods.
Any inputs on this will be highly appriciated.
Regards
SRM USER
hi,
See teh foll notes:
Note 940495 - Requirements not removed from the sourcing cockpit
Note 948716 - External requirements reappear in the Sourcing Cockpit
BR,
Disha.
<b>Pls reward points for useful answers.</b>
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
<b>Please try this -></b>
Have you scheduled the report as background jobs ??
1.CLEAN_REQREQ_UP
2.BBP_GET_STATUS_2
To test it once, if this helps...run these report using SA38 transaction without giving any input parameters.
Requirement will disappear in both the cases from sourcing cockpit, once PO is created.
Look at history of this requirement. Sometimes backend system post already purchased items to SOCO. There is a SAP Note 948716 for this problem
To delete the unwanted SC's from the SOCO list,you can implement the BADI "BBP_WF_LIST".Here you can write the logic for removing the unwanted SC's(based on the Old Po's) from the Sourcing cockpit i.e. Modify the List of SC's displayed in the Sourcing Cockpit.
Alternatively,you can also create a WF whereby you can reset the SOurcing indicator for the Old SC's so that they dont appear in the Sourcing cockpit.
<u>Related links -></u>
Do let me know.
Regards
- Atul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.