on 10-23-2007 10:42 AM
dear all!
i have following request for delivery in sales process. during picking i want to post the goods automatically from unrestricted to project stock.
can you think of a way using sap standard documents/processes instead of using a bapi for stock posting from unrestricted to project stock? would lean wm be suitable?
thank for your help!
matthias
thank you for you answers. i want to post goods issue regulary with vl02n from project stock. i need a step before that transfers the goods from unrestricted to project stock.
Message was edited by:
Matthias Rumplmaier
Matthias,
Check movement type 313,314Q etc..
Assign it to ur schedule lines in VOV6
REWARD If this helps...
Regds
MM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You need to make sure a schedule line exists in sales order (item>schedule lines).
That particular schedule line should have a movement type assigned to it. So when u create a delivery and do a PGI it will automatically post it.
Reward if it helped.
Chandru
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mathias
Check with the Movement types for moving Goods from unrestricted to Project stock.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.