on 10-22-2007 10:33 AM
Hi,
can anybody give me direction to get report of modelwise first date of production.
Means i shall give the list of material and required output is date of first material production
regards,
Bharat
Hi Bharat,
letme give some inputs,
have u created any production order for your list of materials.
suppose if two materials have same production dates, inthat case what is your requirement.
could u explain more in detail
regards
pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
i hope you are using Modelmix in production line in REM. Inthat case for every material u should have planned order AM i correct. If so u can use Table PLAF .
if u give your material list here, u will get order start date and finished date (see the fields PSTTR,PEDTR). u can sort ur planned order based on date.
I hope this will solve ur problem
regards
pradeep
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.