on 10-19-2007 11:12 AM
Hi,
We have given the following plant with business area, but the user could change the plant with other business area.
Plant: 1100, 1200
Business Area : 1100,1200
So we need to write a validation, could any one help me how to do validate both, so that if the user enter 1100 plant with 1200 Business area he should get a warning message.
Rgds,
Prasad
Hi Prasad,
The Validation can be applied both at the wbs & project level....
1. For Project Or wbs:
SPRO VIEW: Project systems --structures - operative structures- WBS-- maintain validation
click on the project or wbs as required.
Create a new validation & name it. create a step inside the rule... by clicking validation & step buttons available.
Now give the prerequisites You can give project profile , type & BA as prerequisities for your requirement by selecting the same from the table fields on the right of the screen
next for check --- select the plant field and give the value..as required for the BA.
for msg --- you have to create a msg type and maintain the number...here and save your validation.
For two BA you can have three steps maintained in the validation...
Assign this validation to your required project profile and tick the Auto validation button available in the profile.
Hope this helps you.
Rgds,
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.