on 10-18-2007 4:04 PM
Hello,
is it possible to copy the Business Blueprint Structure (navigation tree on the left side of SOLAR01) from one Implemenetation project to another?
I have to copy only the structure, not the documents.
Thanks,
Manuel
Yes it is possible.
When you go to SOLAR01 select the Business Scenarios folder on the left side of the screen and have the structure tab selected on the right. Make sure the Source field (on the right) is set to Project. When you click the drop-down in the Scenario Name column you can then bring in the structure from any of your projects.
You then have the option to ignore documents, refer documents or copy documents. Obviously mark the radio button to ignore documents for your case.
Hope this helps,
Nathan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You get 10 points! Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.