Dear Experts,
Plz tell me the Diff Between Schedule start,end & Basic start, end date in Process Order
Regards
Sumit Kalyan
Hi,
In addition in transaction md01/md02 in the scheduling option 1 is for basic date scheduling & 2 is for lead time scheduling.
In-house production time is used to calculate basic dates & floats from schedule margin key is used for lead time scheduling.
Regards,
Senthilkumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
when sheduling the planned order the system take the basic dates.
When you convert the planned order into production order the operation lead time and floats are taken into consideation.i.e lead time sheduling.
1.Basic finish(end) - inhouse production = basic start
2.Finish (end) time + float after production= Sheduled finish time
Start + float before production=Sheduled start time
Thanks and regards
Murugesan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.