Diff Between Schedule start,end & Basic start * end date in Process Order

Former Member
0 Kudos

Dear Experts,

Plz tell me the Diff Between Schedule start,end & Basic start, end date in Process Order

Regards

Sumit Kalyan

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184627
Active Contributor
0 Kudos

Hi,

In addition in transaction md01/md02 in the scheduling option 1 is for basic date scheduling & 2 is for lead time scheduling.

In-house production time is used to calculate basic dates & floats from schedule margin key is used for lead time scheduling.

Regards,

Senthilkumar

former_member698542
Active Contributor
0 Kudos

Hi,

when sheduling the planned order the system take the basic dates.

When you convert the planned order into production order the operation lead time and floats are taken into consideation.i.e lead time sheduling.

1.Basic finish(end) - inhouse production = basic start

2.Finish (end) time + float after production= Sheduled finish time

Start + float before production=Sheduled start time

Thanks and regards

Murugesan