on 09-19-2017 9:28 PM
Hi,
Do I need to implement IBP S&OP before Response & Supply or can I implement IBP Response & Supply directly?
Best regards
Jean-Guy Pariseau
Hi Jean
You can implement Response & Supply first if you want to, using SAP74 PA. But you have to make sure that, if later you want to implement S&OP modules (DP/IO/CT) you will have to use IBP1 PA and have to integrate KF data between those two PA.
Note - IBP1 will soon have Response & Supply planning area KF's too. Check with SAP on exact dates.
Regards
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Order Base Planning in the Unified Planning Area will be available from IBP 1802 release on: https://www.sap.com/documents/2017/06/f21b5a93-c37c-0010-82c7-eda71af511fa.gate.html
Regards,
Ivan
Hi Ankur,
It is the page for the IBP Roadmap, please look for Integrated Business Planning on the root page in that case:
https://www.sap.com/products/roadmaps.products-solutions.html
Regards,
Ivan
Hi Jean,
The customer can implement Response and Supply without other modules.
IBP implementations start from the S&OP, Demand (Time series) and then Response & Supply (Order Based), so far no one implemented Response and Supply modules directly.
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jean-Guy
i dont know exactly, but now i am implementig response and supply only with the sap 74. we dont need S&OP
Regards
Jorge
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.