Unnecessary PR's

Dear Gurus

Unnecessary PR's are genarating after MRP run for FERT in Plng strgy 20, in MRP 4 view maintained for HALB and ROH is defined (Individual/coll. 1 ). It was found that for same ROH , PR's are genarating with AccAssCat-"E" and some without with diffrent quantity but requirement is some other while looking to CS11. Why this is happening?. pls suggest a soln 4 this.....

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Oct 16, 2007 at 06:43 AM

    Ragesh,

    It is generally advised to maintain "Collective Indicator - 2" for ROH, as raw material planning and costing need not be sepcific to Sales Order.

    In your case for all Sales order related requirement of ROH, system is creating PR with account assignment category as "E" and for non sales order related requirement it is creating normal PR with no account assignment.

    Regards,

    Prasobh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.