Hi Experts,
Have some doubt on the multiple operations carried out simultaneously We have second operations 0020 carried out parallel in Line 1 , Line 2 and Sub contracted. The first operation is carried out internally with raw materials issued to it. How the material issues to the sub-contracting process and received back in this scenario.