Skip to Content
avatar image
Former Member

Missing purchasing organization in purchase requisition

Hi guys!

I have following problem:

One material with a quota from 01.01.2008 to 31.12.9999

and the quoted amounts are okay.

The purchasing requisition before December work fine, the

field purchase organisation is filled.

But when I take a look at PR from December 2007 the purchasing

organization is missing.

What could be the problem?

Thanks for help,

Barbara

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Oct 15, 2007 at 01:05 PM

    Hi,

    Please check the source list, whether the validity period exists for December 2007 for that material and the Purchasing organization combination.

    Regards,

    DilliB

    Add comment
    10|10000 characters needed characters exceeded