How to find change record in project system(PS)

Sep 19, 2017 at 01:38 AM

52

avatar image

Dear friends,

If you want to check project's all change log (WBS/Network/Activity/Material Component...)by all users, which ways can you adopt?

P.S.: I can only see its last change log by one user... :(

Thank you in advance.

Rgs,

Kudi

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Maria Terence Sep 20, 2017 at 11:27 AM
0

Hi,

Use CN60 transaction

Regards

Terence

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hello,

Thanks for your reply.

CN60 can only find project change document, but its document seems not very clear(same record occurs often).

Users want to conclude all project change log/record at one period...

Regards,

Kudi

0

Hi,

It is not only project change documents, it has Project, WBS, Network and activities.

If you are looking for more specific, then you need to check in Table CDHDR (header) and CDPOS (Change info) and develop the report.

Regards