How to find change record in project system(PS)

Dear friends,

If you want to check project's all change log (WBS/Network/Activity/Material Component...)by all users, which ways can you adopt?

P.S.: I can only see its last change log by one user... :(

Thank you in advance.

Rgs,

Kudi

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Sep 20, 2017 at 11:27 AM

    Hi,

    Use CN60 transaction

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

    • Hi,

      It is not only project change documents, it has Project, WBS, Network and activities.

      If you are looking for more specific, then you need to check in Table CDHDR (header) and CDPOS (Change info) and develop the report.

      Regards

      Terence