Skip to Content

Shifting of Demand Plan by Lead Time

Hi All,

There is a requirement to generate a Loading plan as an output of IBP heuristics. Loading plan is essentially FG Demand plan shifted by Production Lead time.

Is there a standard key figure which shows demand plan offseted by lead time?

Or do we need to build any calculation/transformation.

Let me know your thoughts/approach on the same.


Thanks
Vijay

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Sep 19, 2017 at 09:52 AM

    Hi Viajy,

    Loading plan is not supported in IBP. Can you explain the scenario.

    Best Regards,

    Lingaiah

    Add comment
    10|10000 characters needed characters exceeded