Lead time scheduling: between planned orders of Header and component

Oct 12, 2016 at 03:41 PM

79

avatar image
Former Member

Header Material H:

Routing RH (Planned order H)

Component Material: C

Routing RC (Planned order C)

BOM:

H - Header and C- Component under "H".

In Leadtime scheduling, the "Planned orders of H and C" are not being scheduled , such that the "Finish time" in planned order C is the Start time of planned order "H" as the header H could start only after "Finish time" of "C".

Say Qty : 1 no.

M/c time : 1min each in both routings.

* Both Planned orders show the schedule type: Backwards.

Instead it is scheduled at the same time.

Planned order: H

Production Start Date/Finish Date: 10/20/2016

Finish Time: 22:00:00

Start Time: 21.59:00

Planned orders: C

Production Start Date/Finish Date: 10/20/2016

Finish Time: 22:00:00

Start Time: 21.59:00

---------------------------------------------------

I need it like this. ...

Planned order: H

Production Start Date/Finish Date: 10/20/2016

Finish Time: 22:00:00

Start Time: 21.59:00

Planned orders: C

Production Start Date/Finish Date: 10/20/2016

Finish Time: 21.59:00

Start Time: 21.58:00

** The header and Component are in 2 different routings and hence 2 different planned orders. (Planned order-REM)