Pranjal,
Its not clear from the image which are the PR and PO commitments.
Have a look on OSS to see if there is a suitable OSS Note.
PeteA
Hi All,
Has any one please come across this issue ? Normally once PR is converted into PO , commitment value of PR goes off but in this case commitment value for both PR & PO is showing up . Also, we can not do GR/SES for the PO at this moment . Requirement is to remove the commitment value of PR , tried by deleting the PR but not going off .
Hi Maria,
Even order is done " TECO" , still value of PR is showing as commitment in order .
Thanks for your response .
BR
Hi,
By displaying the order using - IW33- cost overview-Rep.Budget/Commit.-Orders: Commitment Line Items .
Hi Pranjal,
Let us know what is the report you are talking about ?
Your PR get the deletion flag after TECO of order, is the order is TECO and still system shows the commitment. Try to TECO the order and check
Regards
Terence
Hi,
By displaying the order using - IW33- cost overview-Rep.Budget/Commit.-Orders: Commitment Line Items .
Pranjal,
Can you please send a screenshot of the Rep. Budget/Commit. report to illustrate your issue?
PeteA
Add comment