Skip to Content

Commitment Value

Hi All,
Could anyone please let me know any OSS note to fix below bug in production environment .

Commitment value for both PR & PO is showing up in maintenance order .Requirement is to remove PR commitment value, how can we remove it ?
PR is manually created & order no is entered manually in PR as account assignment . PO is created with ref. to the PR . As per standard process, commitment for the PR should be zero, which is not the case here . I have checked by deleting PR line item , but still value
of PR is showing as commitment in maintenance order . We can not set final delivery
indicator in PO since SES is still expected after 3/4 months .

Thanking you in advance .

Pranjal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

8 Answers

  • Best Answer
    Sep 20, 2017 at 07:10 AM

    Pranjal,

    Its not clear from the image which are the PR and PO commitments.

    Have a look on OSS to see if there is a suitable OSS Note.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 15, 2017 at 07:49 AM

    Hi All,

    Has any one please come across this issue ? Normally once PR is converted into PO , commitment value of PR goes off but in this case commitment value for both PR & PO is showing up . Also, we can not do GR/SES for the PO at this moment . Requirement is to remove the commitment value of PR , tried by deleting the PR but not going off .

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 18, 2017 at 05:04 AM

    Hi Maria,

    Even order is done " TECO" , still value of PR is showing as commitment in order .

    Thanks for your response .

    BR

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 18, 2017 at 12:18 PM

    Hi,

    By displaying the order using - IW33- cost overview-Rep.Budget/Commit.-Orders: Commitment Line Items .

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 17, 2017 at 10:07 AM

    Hi Pranjal,

    Let us know what is the report you are talking about ?

    Your PR get the deletion flag after TECO of order, is the order is TECO and still system shows the commitment. Try to TECO the order and check

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 19, 2017 at 05:06 AM

    Hi,

    By displaying the order using - IW33- cost overview-Rep.Budget/Commit.-Orders: Commitment Line Items .

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 19, 2017 at 06:58 AM

    Pranjal,

    Can you please send a screenshot of the Rep. Budget/Commit. report to illustrate your issue?

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 20, 2017 at 06:54 AM

    capture.jpg

    Hi,

    Please find attached the file .

    BR,

    Add comment
    10|10000 characters needed characters exceeded