Skip to Content
avatar image
Former Member

Sub assembly for finish product

Hello All

I have following requirement.

finish product YF1 has sub assembly YI1 and YI2.

My requirement is to drive demand for both sub-assemblies through finish product YF1.

I want to consume YI1 into YF1 but i dont want to consume YI2.

Yi2 will be sent separately to customer.

Please let me know, how to map this scenario

.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 16, 2017 at 09:36 AM

    Maybe a sales BOM can help you. The header of this this sales BOM is YF1, the component is YI2. So when you create a customer order there are 2 items: YF1 and YI2 which can be delivered to the customer. The production BOM includes both materials, YI1 and YI2. For the component YI2 the indicator "relevancy for production" must not be set.

    Regards, Chris

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello Christian.

      Thanks for your reply, i want to have planned independent requirement for YF1 using MD61.

  • avatar image
    Former Member
    Sep 18, 2017 at 04:46 AM

    dear christian wittmann,

    I don't know where to set the relevancy indicator for sub operation, can u tell me where to set it.

    Add comment
    10|10000 characters needed characters exceeded