Load Data from Transactional Cube (Planning Request) to ODS

Dear Experts,

I am entering data in Planning Folder when I press save, data should go from Transactional Cube to ODS.

How to automate the process to change the planning request from Yellow to Green in the Transactional Cube.

Thanks in Advance,

Selva

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • author's profile photo
    Former Member
    Oct 15, 2007 at 08:04 AM

    Ravi Thanks for the support.

    I have created Event & specified in Process Chain, So that it will start and change the request from yellow to green.

    How to trigger the Process Chain from planning folder?

    Is there any way to attach program in the planning folder?

    Thanks,

    Selva

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi !

      You can use FM RSPC_API_CHAIN_START to start a process chain with a starter process set as meta chain start.

      Regards, Philipp

  • author's profile photo
    Former Member
    Oct 11, 2007 at 04:14 PM

    I think it stays in yellow for every 50,000 records or something like that in planning cubes. you may want to verify it though.

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Oct 11, 2007 at 04:37 PM

    You may want to try the following:

    1. Write a program call the FM " RSAAP_Close"request" to close the request after the load.

    2. Once it is closed, then you may use the proces chain to laod the ODS from the cube.

    Put the above processes in a process chain.

    Ravi Thothadri