PM QUERRI

HI PM GURUS

1.How do we do capacity calculation in work centre?

2. How is capacity avialability check performed against work centre while creating order?

3.What is standard value key in work centre for?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • author's profile photo
    Former Member
    Oct 15, 2007 at 07:42 AM

    Hi Kolla........

    In Work Center - Capacity Tab, we mention the No. of Individual Capacities, Capacity Start time, Break Time & Capacity End Time, after this the system automatically calculates the Availability Capacity.

    Regarding Availability Check for Capacity......you need to go to Config Settings for PM.......

    Plant Maintenance & Customer Service>Maintenance & Service Processing>Maintenance & Service Orders>Function & Setttings for Order Types>Availability Check for Material, PRTs & Capacity>Define Inspection Control...

    Standard Value Key means the standard value to be used by work center defined in a Key.

    I hope, you get something from this....

    Regards,