I created a planned order for the Finished product, I converted into Production order.

Iam not getting Planned orders/ Purchase Requisations for my dependent requirements,,

If i check in MD04 for dep items it is showing "ordres" in MRP element. Iam not able to see either Planned Orders/Purchase Req why?

One more thing is there any list to see Pending Planned orders for Dependent requirements.

Thanks in advance

Regards,

srihari.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 11, 2007 at 08:59 AM

    Hi srihari,

    please clarify , whether "dept reuiremets or planned order/ purchse req " not generating. once you convert the planned order to production order , dependent requirments will be converted to reservation for depent items.

    How do you create planned order by manully or by MRP run. For manul creation of planned order, sytem will not create planned order/pur Req automatically for dept items MRP, For that u have to run MRP.

    regards

    pradeep

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi srihari,

      Now the plannd order/purchse requ is getting generated ??

      please letus know at what reason your were not getting previously..

      regards

      pardeep

  • avatar image
    Former Member
    Oct 11, 2007 at 08:44 AM

    Check in MRP4 view of the Finished product whether depending requirement nto be planned box is checked?