on 10-11-2007 5:43 AM
Dear PS gurus,
Request pl help in how to do undo if the Network is technically completed (TECO) applied in Network & saved.
In Project WBS & Definition, we have provision of UNDO or cancel the TECO & Close, but in network, we don't find the undo/cancel in Status, why?
Pl help, thanx in advance
Regards
Srihari
Dear shrihari
Even in network also the same applies as in the case of Proj Def/WBS, i.e. u can undo the teco status. check wether u have activated any user status which stops u doing the reversal.
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Murali,
Thanx & let me know how to chek the network activitation of user or system status ?
Is this thru SPRO, if spro, pl guide me the path to do activation of user or system status, which is more relevant to ?
I would like to mention i am using standard project/wbs/network templates for ps projects.
Best regards
srihari