Project systems report

Hi All,

I developed a report in Project systems ,now I want to validate the output of the report.

The report is cost element wise report for actual/comm/total/plan.

Could you able to give suggestions against which table or standard report or any other data do I need to evaluate?

Thanks,

Anitha

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Oct 10, 2007 at 03:34 PM

    Run CJI3 and check for a project. This is actual line items report, that is standard. Compare the results of your report with this.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 11, 2007 at 03:01 PM
    Add comment