on 10-10-2007 3:40 PM
The stock transfer orders we publish fromo SCM-APO to ECC are fixing a value of 1 in the Planned Delivery Time field of the Purchase Requisition.
I have checked the material master both in APO and ECC there is no 1 value in fixed delivery time.
There isn't an info record for this material in the plant.
There isn't an scheduling agreement.
I have one of our abaps to debbug the program and the value sent from APO is 0.
What else can I check? I will appreciate all your answers
-Italo
Hi
Check this BAdi /SAPAPO/PWB_SOS if this is implemented.
this badi can be used for changing planned delivary time.
-srini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
When we publish the Stock Transfer Orders from APO to ECC, they pick the parameters defined in ECC and not the values passed from APO for eg. the start and the end time, Planned delivery time etc. To correct this issue you have to remove the planned delivery time defined for this particular plant.
For doing this Go to SPRO -
> Enterprise Structure -
> Definition -
> Logistics - General -
> Define, copy, delete, check plant. Select the Plant that you would like to define/change the Plnd Delivery Time.
Hope this will solve your Issue.
Award points if Helpful,
Regards,
Manjit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try to change the value of GR time in Location Product master and see if it has any correlation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.