on 09-14-2017 10:33 AM
Hi Sagar,
No start after is only to determine and restrict a job to run within mentioned time frame. i.e if there is delay more than what is mentioned inthe field the job will not run. This does not mean an end date or time for a job.
Please read sap note 434011 - "no start after" restriction does not work
Reason:You schedule a job with the period 'Hourly'.
First start time: 15:00 No start after 15:30.
The following then applies for the successor:
Start time: 16:00 No start after 16:30.
Regards,
Prithviraj.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sagar,
Can you explain more about your concern?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.