Hi Sagar,

No start after is only to determine and restrict a job to run within mentioned time frame. i.e if there is delay more than what is mentioned inthe field the job will not run. This does not mean an end date or time for a job.

Please read sap note 434011 - "no start after" restriction does not work

Reason:You schedule a job with the period 'Hourly'.
First start time: 15:00 No start after 15:30.

The following then applies for the successor:
Start time: 16:00 No start after 16:30.

Regards,

Prithviraj.

tan_michael
Active Participant
0 Kudos

Hi Sagar,

Can you explain more about your concern?