scenario it is :

in our company time evaluation period is 26-25 month and payroll is 1-31 month,

how to management is? I change pt60 period with v_t549q and TRMAC tables and

I know I can change payroll period with TRMAC table , but we run payroll 1-31month untill now and change date from payroll is not posible , are there any way to forward overtime and absence to next month ?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

avatar image
Former Member Sep 19, 2017 at 03:58 PM
0

Hi,

I have never come across such a requirement however I think the link below should help:

https://blogs.sap.com/2013/06/01/carry-forward-overtime-to-next-month-pay-26th-to-25th/

Thanks
Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

I saw it,it just carry forward overtime and there don't solution about absent and work day is 25 ,not 30!!!!!!!!

0
avatar image
Former Member Sep 23, 2017 at 06:41 AM
0

Hi,

As Richard mentioned it might be solution I had done but it seems a bit complicated.

You know TRMAC is not for Payroll. It is for Time evaluation. You should define your payroll periods as 1 - 31.

You know time evaluation runs day to day. So another solution might be running payroll 1 - 31 and any time after 25th of period by considering it as 1 - 25th not until end of the month. Then run a off-cycle payroll at beginning of next month as adjustment.

Meanwhile, if you are a developer, it is better a functional consultant implement is not by developing.

BR,

Omid

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

hello

tankx, how to run a off-cycle payroll at beginning of next month as adjustment? how to customise and management it?

data for off-cycle must be insert manually and it is not in time management and in payroll!!

must be run Off-Cycle Correction Accounting (Type B)??

plz help me

0
avatar image
Former Member Nov 20, 2017 at 07:40 AM
0

I solved this question with change date in t549q and create zimpt b2 that import zl data in special date.