Hello all,

WBS elements have been created in a project definition, but I'd like to move them into another project definition.

Those WBS element have been already budgeted, so I can't just delete them and create them again in another project definition.

Do you know if it is possible to change the project definition of a WBS element ?

Thank you for your answers.

Philippe

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Documentation confirms project definition cannot be changed if the WBS element has already been budgeted...