Former Member
Sep 14, 2017 at 03:55 PM

Some PO item is not rescheduled after MRP run

69 Views Last edit Oct 04, 2017 at 06:31 PM 2 rev

Hi experts,

I'm having few issues on the MRP run and would like to get your advise.

Material master details

-> MRP type (PD)

-> GR processing time 3 days

-> Availability check 01

-> Lot-to-lot procedure

-> Rescheduling horizon 100 days

1)In MD05, there is available stock in MMBE. However, PO item 10 is being rescheduled to the delivery date where there is sufficient stock. Why does this happen? From what I understand, it should be rescheduled to cover insufficient requirement.

2) Apart from that, in the PO, material 1234 has for eg. 10 line items with different delivery date (Difference by one day). After MRP re-run, systems shows exception message 15 for item 10. For other line item, no rescheduling date is being proposed.

Any idea on this? Appreciate your help as I've been searching but have not found an answer.

Thank you.