Hi experts,

i'm trying to understand the behavior of a DTP in a process chain.

This is my scenario:

BW 7.5 SP7

The process chain load a DSO in Full Mode from different sources.

The last step is a DTP that load the DSO with itself, for updating some fields.

Now, there are two indexes, that are not updated by any routine, which are systematically reset to 0 when the process chain is over.

If i run manually the DTP the two indexes keeps their own values.

Launching the DTP through process chain get different result from manual launch, i try to create a new DTP, i try to insert the DTP in a MetaChain, i try to execute the DTP through an ABAP Program recalled by the process chain but i get the same result, only the manual launch produces the correct result.

I don't understand why, it's possible to debug the process chain?

Any ideas?

Thank you.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 19, 2017 at 01:04 PM

    Hi Giordano,

    Do you have any reference to the execution user, e.g. sy-uname in the transformation?

    Kind regards,
    Andrey

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 19, 2017 at 01:48 PM

    Hi,

    no, there is no reference to the execution user in the transformation...

    Add comment