Skip to Content
avatar image
Former Member

BOM Usage

Good Day.

I have a scenario as follows:

FERT: 1001

ROH: 2001

When I create sales order for FERT 1001, when I run MRP, I want the system to create planned order or PR for ROH 2001, same quantity as 1001.

Let me know which BOM usage should I use?

We will not use PP/production order for this. Just Sales Order and Purchase Order.

Thanks,

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Oct 09, 2007 at 01:44 PM

    I think you need a production BOM and a production order. Then the production order transfer the requirment to the ROH material.

    Roberto

    Add comment