Backflush with no BOM

Can I Backflush a Finished Good that has no BOM but has a routing with materials assigned to the Component allocation?

Kind regards,

Guy.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

5 Answers

  • Best Answer
    avatar image
    Former Member
    Oct 09, 2007 at 11:38 AM

    Guy

    It is impossible to assign componets to a Routing without a bom ACCORDING TO MY KNOWLEDGE.

    SAP will not allow you to assign component and it will ask to create a BOM

    BR

    SK

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 09, 2007 at 11:31 AM

    Hi

    The back flush functionality is for components & not for the materials.

    I hope you are referring to materials assigned means header materials assigned to routing.

    If my assumption is correct, it is not possible to backflush.

    Regards

    YMREDDY

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 09, 2007 at 11:35 AM

    Dear Guy Hall,

    Can you please tell me whether your finished product has got a production

    version,product cost collector?

    Regards

    Mangal

    Add comment
    10|10000 characters needed characters exceeded

  • Oct 09, 2007 at 12:00 PM

    Dear Guy,

    What Mr.Ganesan has asked is a valid question ,once if your material is not

    having a valid BOM,you can not carryout the Component allocation in rate routing.

    The system pops up whetehr you want to create a BOM.

    Regards

    Mangal

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 09, 2007 at 12:45 PM

    Hi Guy

    first of all like above been told , you cant assign material in routing without BOM

    and Backflush means issue of component , which is BOM items

    Cheers

    Bala