Former Member

Final Preperation Activities

Dear All,

We have completed our development with all the testing. Now before going live i would want to do a final preperation for going live. I would like to know what are the activities we need to do for final preperation. Please help.

Regards

Vijay

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Oct 09, 2007 at 10:16 AM

    Hi Chandra

    These are the Activities

    <u>Final Preparation phase</u><b>Setup Production Environment</b>

    Define Production System Design

    Set Up Production Environment

    <b>Confirm BW Production Configuration</b>

    Execute BW Test Plans in Production Environment

    <b>Conduct System Tests</b>

    Conduct System Administration Tests

    Conduct Backup and Restore Procedure Test

    Conduct Failure Scenarios Test

    Conduct Disaster Recovery Test

    Conduct Going Live Check

    <b>Training Plans</b>

    Develop End User Training and Documentation Content based on Best Practices

    Prepare for End User Training and Documentation Delivery

    Deliver End User Training

    Train System Administration Staff

    <b>Define Long-Term Production Support Strategy</b>

    Refine Production Support Plan

    Reorganize Team for Production Support

    Establish Help Desk

    Realization Review

    <b>Final Preparation Tasks</b>

    <b>Transport to Production Environment</b>

    Perform Conversions

    <b>Cutover</b>

    Perform Cutover to Production System

    Confirm Production Readiness

    Verify Users are Ready

    Final Preparation Review

    Conduct Quality Check

    Conduct Final Preparation Review

    Sign off Final Preparation Phase

    Final Approval for Going Live

    Hope this helps.

    Thanks

    CK