Asset under construction

Hi,

Can anybody send me steps for Asset under constraction,

Thanks in advance

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Oct 09, 2007 at 07:43 AM

    There are different options for AuC.

    Do you produce the assets yourself?

    Then I would suggest to create an internal order for the asset and settle it to the AuC.

    If you want to use AuC for different asset related invoices you receive, you can post these invoice to a clearing account for AuC and use transaction ABZON for activating the asset itself.

    Regards,

    Johan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 09, 2007 at 09:34 AM

    Hi,

    You can maintain two types AUC accounts.

    <b>1.</b> Suppose you want to post all expenses directely to AUC, need to create AUC under class 4000

    Posting are made through F-90

    Entry for example

    AUC a/c dr

    To vendor or bank account

    Go to AIAB ---> Give distribution rule and

    go to AIBU --> Settle the asset

    Entry passed is

    Asset a/c Dr

    To AUC a/c

    The advantage of this is you can settle this AUC (4000) whenever you want.

    <b>2.</b> You can pool cost in internal order and can settle AUC afterwards

    Asset settlement thought internal order is general used for assets under construction. All costs are pooled in the internal order. Periodically or whenever wants the internal order is settled (within a fiscal year) i.e. the amounts in the internal order are capitalised.

    First create an internal order (KO01) , take object class as investment and give investment profile. Now system asks and creates one AUC account under asset class 4001.

    Then create settlement rule (KO02) and release the order (control data tab)

    Post some amounts (like wages or non-production material ) to internal order.

    Then come to KO88, first take the automatic settlement and run.

    The accounting entry passed is

    Asset under construction a/c Dr

    To Wages a/c

    If you want to complete the settlement to auc, then take now full settlement option and run

    The accounting entry passed is

    Asset a/c Dr

    To Asset under construction a/c

    While doing settlement in KO88, you can give any settlement period, posting period and asset date, but all should be in the same fiscal year.

    If you want to close the order go to KO02, give order number and take control data tab and click on technical complete tab on the screen and save. Internal order will be closed.

    Radha