Add an overdelivery tolerance on the work scheduling view of the material master. It can be entered as a percent which will allow for over delivery up to a percentage above the order quantity or as unlimited which will allow unlimited delivery over the order quantity. I prefer to use the percentage since while most orders can have some reasonable amount of overdelivery but at some point the entry is probably a mistake. For example with unlimited, an order for 1,000 could be confirmed for 10,000 without generating an error. I think it's better to determine how much over the planned quantity an order can reasonable go and then enter it as a percentage. For example, an order for 1000 with an OD tolerance of 10% would allow you to confirm up to 1100 before generating an error.
Hope this helps.