Skip to Content
author's profile photo Former Member
Former Member

Appropriation request issue

Hi SAP experts,

I need help with an issue involving approp requests/projects:

1) There is an Approp Request created and I did not release.

2)There is a Project created and I did not release and did not budget it.

I managed to create a PO and could save it normally without a problem. I shouldn't be able to requisition against an Approp Request that was NOT released or an unbudgeted Project.

Any ideas why it happened ?

Regards

Roger

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Oct 09, 2007 at 01:34 AM

    Check that your inv program is assigned to a budget profile.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.