on 10-08-2007 8:34 PM
Hi Gurus,
I am going to do a functional upgrade from 4.7C to ECC 6.0 (classic GL, not new GL). Can someone please list me the steps that I need to do to achieve the upgrade.
I would be very grateful and would assign points as a gesture of appreciation.
Thanks
Chandan
If you are not going to implement new g/l, then all you have to do is test if all the transactions that the client is using are wokring fine in ECC 6.0 or not.Do the unit testing and integration testing and get business sign off.
Assign points if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.