BOM explosion while creation of scheduling agreement / PO

Hi all,

Can anyone pls tell me how can i control / make settings for the explosion of BOM, when MM creates a scheduling agreement or a PO ?

Also, if i have multiple alternative BOMs, how can i get the BOMs selected automatically??

Thank you,

Shrenik

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Oct 07, 2007 at 05:07 PM

    it is not clear from your question?

    When creating SA/PO, why you want the BOM to be exploded? what is the apllication you are talking about?

    Please explain in detail

    Add a comment
    10|10000 characters needed characters exceeded

    • Shrenik,

      It would have default picked up the first available BOM, probably you would have used the same in Production Version also, that is the reason you are not able to apperciate the importance of Production version.

      check and see if you are able to pick up the 2nd or 3rd BOM without production version.

      Regards,

      Prasobh

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.