on 09-11-2017 11:37 PM
availability-check-z3-confi.jpgreq-class-z1-mto.jpg
Hi Experts
We have MTO scenario using customised planning strategy Z1. Planning strategy uses requirement class Z1 which has special stock E - Orders on hand and account assignment category M -Ind. cust. w/o KD-CO. Please find attached requirement class screenshot. We follow below steps.
1. Sales order creation and its not confirmed during creation
2.MRP run and getting Intercompany purchase requisition
3. Convert purchase requisition to PO. (PO has sales order info)
4. Sales order availability check and its confirmed
We have an issue with sales order confirmation. If we run sales order availability check, Order would be confirmed.Open PO confirms the sales order.
We don't want sales order confirmation until we get the stock from purchase order in this scenario. I deactivated OPJJ availability scope of check confi and tried sales order confirmation. But still it confirms the sales order. Could you please suggest how to avoid sales order confirmation till we get the stock from purchase order ( E stock)?
Hello
You already unchecked the flag include purchase orders, so the PO should not be included in the ATP check. Did you try to create a new sales order after the configuration changes? Can you please provide the results of the ATP check in CO09?
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.