Replenishment TO is always created in base unit of measure, We need it in alternative UOM

Sep 14, 2017 at 05:32 AM

43

avatar image
Former Member

Hello,

We are creating automatic fix bin replenishment as per standard scenario. Replenishment TO is always created in base unit of measure. We want that it should be created in alternative unit of measure. Is there any way we can achieve?

We have already done below action but it is not resolving the issue

(1) Maintained alternative unit of measure in material master

(2) We have already maintained value L in material master WM-1-"Prapose UoMfrm mat"

Thanks,

Milind

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Mona Lisa Sep 14, 2017 at 09:32 AM
0

Do you have value maintained in WM unit of measure in WM1 view,

Even if you have maintained L- Propose WM unit of measure and WM unit of measure field not having value system will pick base unit of measure


ridib.png (4.1 kB)
Show 1 Share
10 |10000 characters needed characters left characters exceeded

In the case of replenishment all the data in WM2 view is in Base unit of measure hence TR is also in Base unit of measure. So with value WM unit and Value L still system create TO in Based unit of measure as the reference document (TR) is having UoM as EA,

you need to change the value from L to M , but look at the impact on other process before finalizing