PP's Availability Date is wrongly set

Sep 12, 2017 at 01:57 AM

61

avatar image
Former Member

Hi All,

How can we set the calendar (working time ) to define the GR process Time?

Example:

When we set '24:00:00' in GR processing time, it will be 3 days if it's calender setting for working hours is 8 per day.

This is what we would like to do. But I don't know how to set calendar.

Please kindly light us.

Regards,
Thiri

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Sandeep Y R
Sep 12, 2017 at 08:50 AM
0

Dear Thiri,

GR process time is time between receipt of a product and adding it to stock.

When you set '24:00:00' in GR processing time this is understood as 1 day which is nothing but 24 hours.

In any Site we have Operating Hours i.e Site Work time , lets say from 9:00 to 17:00 and Site Calendar i.e Site Working days, Lets say Monday to Friday.

When you perform MRP(Material Requirement Planning) , System will consider your Site working day calendar , system will not consider on weekends , Hence the Availability date is calculated as Planned delivery date & Goods receipt processing time i.e 24 hours.

Regards,

Sandeep

SAP Support