Hi Team,

I have two category of Employees weekly 35hrs and 38 hrs.

In OM PP01, IT1011 (Work schedule) currently its defaulting 35 hrs and if change to 38 hrs per week its calculating percentage as 108.57% which is wrong.

Can someone suggest how to remove default.

I say below thread but not sure what values to maintain

https://archive.sap.com/discussions/thread/1924564

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Sep 25, 2017 at 11:52 AM

    Hi

    The amount in default part is set according Hours per week , therefore please change the number of hours in this part and after that the amount in default value will change.

    Regards,

    Shirin

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 25, 2017 at 11:22 PM

    Hi Shirin,

    I am not able view "work schedule group" to pick in IT.

    I have two employee group of employee one having 35 hrs per week and other 38 hrs.

    Can you pls help

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 28, 2017 at 11:03 PM

    Hi Shirin... I am not seeing

    Work Schedule Group (drop down) in my infotype

    can you help

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 29, 2017 at 05:00 PM

    The Default Values come from parameters from Group WORKT in table T77S0.

    Try t-code spro SAP Reference IMG > Personnel Management > Organizational Management > Infotype Settings > Working Time > Maintain Rule Values and read the related documentation (and maybe also check help.sap.com)

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Remi,

      Default is maintained as 7 hours per day and 5 days a week making it 35 hrs per week.

      But the issue is I have some employees for whom 7.6 hrs per day with 38 hrs per week should be defaulted.

      How can I achieve that. (i did grouped them as seperate)