Hi All,

i have an issue with the position dates, for one position the dates have been delimited.

position 1 - from 04/01/2006 to 05/14/2006

position 1 - from 05/15/2006 to 12/31/9999.

but i wanted the validity dates should be 04/01/2006 to 12/31/9999. i don't need the second option.

Is there any table or screen where i can change the validity period. Even i tried to change from the screen PPOME, which is not accepting. Please help me out on this.

Points to be rewarded.

Thanks,

vasu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

U can do this by using SPRO Settings which is functional job.

and the other thing is u can also try using PP01 transaction and

change the validity dates for the position.

Regards,

Manian.

Answers (5)

Answers (5)

Former Member
0 Kudos

solved by slef

Former Member
0 Kudos

Hi,

Yup u can change the the periods if u go in the change mode, pp02, kindly do the necessary changes and save.

Hope this resolves this issue.,

let me know if u have any concern,

Reward if helpful,

Regards,

Asha

Former Member
0 Kudos

Hi Asha,

Thank you for your answer, i just went to that screen if i give position number and infotype and then if i go to change screen it is asking only the object abbreviation and Object name, here i cannot change the dates, is there any other way to do this.

Former Member
0 Kudos

Use PP01

Enter the object type & id

Select object infotpe

Select CREATE function from toolbar

Overwrite start date with first record start date and end date with second/last record end date. Enter the Abbreviation & description you want and hit save.

The system will return a warning it will delete/delimit overlapping records . Go-ahead and save the record.

This will merge two IT1000 records into one.

Reward points if this was helpful.

Regards

Ravikumar

Former Member
0 Kudos

Dear Ravikumar Gurumoorthy

I went all the way through the registation process only to thank you for this contribution. It was very usefull to me. And I am sure that this piece of advice will save me a lot of frustrations in the future. Thank you very much!

Best Regards

Rikke

Former Member
0 Kudos

Hai..

try these two reports..

re_rhgrenz4, re_rhbegda0

Former Member
0 Kudos

Tcode - RE_RHGRENZ4 / Report - RHGRENZ4 can be used for changing the end date. This program contains lot of parameters and this can be used for changing infotype end date.

Former Member
0 Kudos

Hi,

Use transaction -PP01 ->change validity period.

Otherwise try in PP02.

All the Best!!

Regards,

Manoj.

Former Member
0 Kudos

Hi,

You may try the "Editing Period" in Simple Maintenance.

Hope this helps,

Reward points if helpful,

Thank You,