In CO11N, i have 6 activity types. 4 of them have routing data, meaning times needed
HOwever when i'm trying to do CO11N, it didnt show me the Planned to bE confirmed (02.png)
Hi Chin,
Check the formula key that u assigned to QA/Load Matl time activity in CR02. Correct the formula there.